September 8, 2011 |
|
The Old Conant (Park Ave wing). Ready to be demolished (the bricks were gone, apparently taken away by YB) |
October 6, 2011 (Thursday) |
|
The demolition started at 9 AM, Wednesday. My battery was dead so I had to wait until Thursday morning |
October 7, 2011 (Friday) |
|
After two days |
October 11, 2011 (Tuesday) |
|
Two window units a day...... THe wing is vanishing rapidly |
October 12, 2011 (Wednesday 5 PM) |
|
Demolition is completed. The last part went quickly - you can see the videos (link below)
|
October 21, 2011 (Friday) |
|
A week after, the basement is excavated |
October 26, 2011 (Wednesday) |
|
A week after, the basement is excavated completely |
October 30, 2011 (Sunday) |
|
We had an early NorEaster and the ground is covered with snow |
November 11, 2011 (Sunday) |
|
The ground is cleared, ready for the foundation |
November 17, 2011 (Sunday) |
|
The concrete foundation is started on the South Wing |
December 14, 2011 (Wednesday) |
|
The structure is almost done on the South Wing |
December 22, 2011 (Wednesday) |
|
The structure is up on the South Wing. The inside work has been started. |